City of Wichita - 2006 Status Report - Central Rail Corridor Grade Separation Project
Friday, May 16, 2008 :: Currently 51 degrees in Wichita

Woman reading newspaper

Community Relations
City Hall, 13th floor
455 North Main
Wichita, KS 67202

Hours:
8 AM-5 PM
Monday-Friday

Phone: (316) 268-4351
Fax: (316) 268-4519

Dale Goter
Government Relations Director

Van Williams
Public Information Officer

Lauragail Locke
Marketing Services Director


View archived news releases by year:

Leaving City Of Wichita Website


Status Report - Central Rail Corridor Grade Separation Project

Date: August 18, 2006
Contact: Christopher M. Carrier, Director of Public Works
E-mail: CCarrier@wichita.gov
Phone: (316) 268-4497

 

In April 2005, the City of Wichita began the construction of the Central Rail Corridor Grade Separation Project in downtown Wichita. This project will result in new grade separations along the BNSF Railroad right-of-way at 13th Street, Murdock, and Central, and new grade separation bridges at 1st and 2nd Streets. The total cost of this project is $98 Million dollars, made up of a combination of federal, state, local, and railroad funds.

As of this date, the project is about 40% complete with 37% of the construct time used. All piling for the initial phase of the bridge construction is completed with bridge abutments constructed at 13th  Street, Murdock, and Central. Abutment work continues at 1st and 2nd Streets. Bridge beams for 13th Street are to be installed next weekend.  As a part of this project, the Douglas Street Bridge is being rehabilitated, and this work is about 30% completed.

The project also includes T-Wall retaining walls on both the east and west sides of the rail right-of-way to allow elevation of the rails between the bridges. The west side wall is currently under construction and is about 65% complete, with 2700 out of 4,000 panels placed.  During the placement of the upper row of panels, some rust was detected  on the back face of some of the panels. Further investigation found that the rust was caused by insufficient concrete cover over some of the reinforcing steel. For this reason, these wall panels have been rejected by the City and will be removed from the project. New upper row wall panels will be fabricated by the supplier and placed by the contractor.

Because of the problems with the upper panels, the City, its engineers, and the railroad are examining all of the other wall sections as well. At this point, all retaining wall work has been stopped until our investigations are complete. If additional concerns are found, it will be up to the contractor to correct them at no cost to the City.

The construction of this project should be completed in the fall of 2008.

Back to Top

Printer Friendly Version


  © Copyright  2008 City of Wichita / 455 N. Main, Wichita, KS 67202