Page Content
Wichita Public Works & Utilities celebrated the completion of the improvements on 13th street between Hydraulic and Oliver during a ribbon cutting today. The road was widened to five lanes as part of an arterial street improvement project. Sidewalks were also widened and drainage systems were upgraded as part of the project. Cornejo & Sons, Inc. constructed the improvements over a two-year period that began in August 2012. The total cost is $17.3 million. The project is located in Wichita City Council District I which is represented by Wichita City Council Member Lavonta Williams.