The Oversight Steering Committee has had several planning meetings and the first public meeting will be on October 11, 2019, to discuss the current status of the project. The City will submit its application for WIFIA financing by October 30, 2019.
According to the project timeline, dirt work is expected to begin in early 2020. The official groundbreaking would occur late 2020, following environmental permitting.
Under the current project schedule, the new water treatment facility is expected to be operational by the end of 2024.